.ess_essmenu_ctlessmenu_spmbctr {border-bottom: Transparent 0px solid; border-left: Transparent 0px solid; border-top: Transparent 0px solid; border-right: Transparent 0px solid; background-color: Transparent;} .ess_essmenu_ctlessmenu_spmbar {cursor: pointer; cursor: hand; height:0;} .ess_essmenu_ctlessmenu_spmitm {cursor: pointer; cursor: hand; color: Transparent; font-size: 12pt; font-weight: normal; font-style: normal; border-left: Transparent 0px solid; border-bottom: Transparent 0px solid; border-top: Transparent 0px solid; border-right: Transparent 0px solid;} .ess_essmenu_ctlessmenu_spmicn {cursor: pointer; cursor: hand; background-color: Transparent; border-left: Transparent 0px solid; border-bottom: Transparent 0px solid; border-top: Transparent 0px solid; text-align: center; width: 5;height: 0;display:none;} .ess_essmenu_ctlessmenu_spmsub {z-index: 1000; cursor: pointer; cursor: hand; background-color: Transparent; filter:progid:DXImageTransform.Microsoft.Slide(slidestyle=PUSH,Bands=3) ;border-bottom: Transparent 0px solid; border-left: Transparent 0px solid; border-top: Transparent 0px solid; border-right: Transparent 0px solid;} .ess_essmenu_ctlessmenu_spmbrk {border-bottom: Transparent 0px solid; border-left: Transparent 0px solid; border-top: Transparent 0px solid; border-right: Transparent 0px solid; /*background-color: White; height: 1px*/;} .ess_essmenu_ctlessmenu_spmitmsel {background-color: Transparent; cursor: pointer; cursor: hand; color: Transparent; font-size: 12pt; font-weight: normal; font-style: normal;} .ess_essmenu_ctlessmenu_spmarw {/*font-family: webdings*/; font-size: 10pt; cursor: pointer; cursor: hand; border-right: Transparent 0px solid; border-bottom: Transparent 0px solid; border-top: Transparent 0px solid; display:none;} .ess_essmenu_ctlessmenu_spmrarw {font-family: webdings; font-size: 10pt; cursor: pointer; cursor: hand;} .ess_essmenu_ctlessmenu_spmitmscr {width: 100%; font-size: 6pt;} 拉林铁路全线牵引变压器安装完成-首页-中国中铁电气化局集团公司

拉林铁路全线牵引变压器安装完成

——

日期:2020-08-14  作者:杨永乾  来源:西安电化公司  浏览:4245      【

8月10,随着亚搏体育app官网登录电气化局西安电化公司承建的拉(萨)林(芝)铁路林芝110千伏变电所牵引变压器的安装就位,拉林铁路全线9座牵引变电所的18台牵引变压器全部安装完成。牵引变压器是电气化铁路牵引变电所的“心脏”,是电气化铁路建设的控制性节点、整个电力牵引系统施工的核心环节。

拉萨至林芝铁路是国家“十三五”规划重点工程项目,全长435公里,设计时速160公里,是西藏首条电气化铁路。

 

施工后的米林牵引变电所

 

技术人员正在拉林铁路林芝牵引变电所安装设备

 

技术人员在拉林铁路西藏林芝牵引变电所安装主变压器

 

技术人员在米林牵引变电所安装设备

 

 

 

相关阅读